To create a new project order (PO) in COS:
- Log in to COS and select "Project".
- Click "New Project".
- Choose the "Client" for the project.
- Enter the "Project Name".
- Select "Patch Thru" as the Project Template.
- Click "Create New PO".
General Information:
7. Select the "Start Date" and "Start Time".
- Select the "Stop Date" and "Stop Time".
- Select the "State".
- Enter the "Caller ID".
- Enter the "Number of Questions".
- Assign a "SubClient" if applicable.
- Enter any "Campaign Notes".
- Click "Save".
Entering the Script:
15. Click "Script".
- Copy/paste or type the script into the opening.
- Click "Save and Next".
- Copy/paste or type the script into Question 1.
- Click "Add Response".
- Enter the "Response".
- To create a patch over response, type [transfer= ].
- Set the appropriate "Skip Logic".
- Click "Save and Next".
- Repeat steps 18-22 for any additional questions.
- Copy/paste or type the script into the closing.
- Click "Save and Review".
Upload the Data:
27. Click "Campaign Data".
- Choose "Upload Campaign Data".
- Drag/drop or select the data file to be uploaded.
- Click "Upload".
- Choose the "List Processing" type.
- Ensure the Phone, Name and ID fields have the correct columns selected.
- Add "Misc Send Fields" if applicable.
- Add "Misc Databack Fields" if applicable.
- Click "Save and Next".
Scrub the Data:
36. Select "Campaign Database".
- Click "List Scrub".
- Choose "Mark Cells as Wireless".
- Click "Run Action".
- Choose "Mark Litigator Numbers as Status DNC".
- Click "Run Action".
Determine the Goal:
42. Click "Edit PO".
- Select "Goal Info".
- Select "Targets" as the "Goal Type".
- Select the "Target Field".
- Select the "Target Field Alternate Sort" if applicable.
- Select "CP" as the "Complete Code" (Complete Patch).
- Enter any "Goal Notes".
- Click "Save".
- Enter the number of patches required per target/day.
- Click "Save".